PMP考试模拟试题(40题)


    考前模拟试题
    Disclaimer These questions are intended for study purposes only Success on these questions is not indicative of success on the Project Management Professional Certification Examination This download of the Sample Exam Questions is for your personal use and NOT FOR commercial use Any unauthorized use or duplication of this document is prohibited
    1 A narrative description of products or services to be supplied under contract is called
    a The project plan
    B A statement of work
    C An exception report
    D A Pareto analysis

    2 An example of scope verification is
    a Reviewing the performance of an installed software module
    B Managing changes to the project schedule
    C Decomposing the WBS to a work package level
    D Performing a benefitcost analysis to determine if we should proceed with the pro

    3 Which of the following is not an example of a source of scope change
    A A variation in government regulations
    B Failure to include a required feature in the design of a telecommunication system
    C A need to engage in bottomup cost estimating
    D Introducing technology that was not available when scope was originally defined

    4 The subdivision of major project deliverables as identified in the scope statement into smaller more manageable components is called
    a Parametric estimation
    B Scope definition
    C Feasibility analysis
    D Benefitcost analysis

    5 The process of establishing clear and achievable objectives measuring their achievement and adjusting performance in accordance with the results of the measurement is called
    a Strategic planning
    B Alternative objectives inventory
    C Management by objectives
    D Contingency planning

    6 Configuration management is
    a Used to ensure that the description of the project product is correct and complete
    B The creation of the work breakdown structure
    C The set of procedures developed to assure that project design criteria are met
    D A mechanism to track budget and schedule variances

    7 A fundamental tenet of modern quality management holds that quality is most likely to be achieved by
    a Planning it into the project
    B Developing careful mechanisms to inspect for quality
    C Striving to do the best job possible
    D Conducting quality circle activities

    8 Your most recent project status report contains the following information BCWP 3000 ACWP 3500 and BCWS 4000 The schedule variance is
    a + 1000
    B + 500
    C 500
    D 1000

    9 Learning curve theory emphasizes that in producing many goods
    a Cost decreases as production rates increase
    B Average unit cost decreases as more units are produced
    C Materials become cheaper when they are purchased in bulk
    D Laborers become more productive because of technological advances

    10 Rearranging resources so that constant resource levels are maintained is called
    a Floating
    B Leveling
    C Restructuring
    D Crashing

    11 The _________ is a timephased budget that will be used to measure and monitor cost performance in the project
    A Work breakdown structure
    b Project schedule
    c Cost baseline
    d Cost budget

    12 To transfer most of the cost risk to the contractor the client may use a ___________ contract
    A Cost plus award
    b Cost plus incentive fee
    c Cost plus fixed fee
    d Fixed price

    13 An appropriate sequence for risk management activities is
    a Risk identification risk quantification and risk response development and control
    B Risk identification risk assessment and risk planning
    C Risk identification risk mitigation and risk management
    D Risk identification risk elimination and risk mitigation

    14 Theory X holds that
    a Quality improvements lie in the hands of quality circles
    B Profits are tied to meeting schedule deadlines
    C Absenteeism is tied to poor working conditions
    D Workers are inherently unmotivated and need strong guidance


    15 All of the following are characteristics of parametric estimating except
    a Historical information
    B Quantifiable
    C Scalable
    D Activity lists

    16 Inputs to cost budgeting include all of the following except
    a Cost baseline
    b Cost estimate
    c Work breakdown structure
    d Project schedule

    17 Inputs used during scope planning include all of the following except
    a Constraints
    B Project charter
    C Budgetcost analysis
    D Product description

    18 Cost control outputs include all of the following except
    a Estimate at completion
    B Budget updates
    C Revised cost estimates
    D Cost baseline

    19 Risk identification outputs include the following except
    a Decision trees
    B Inputs to other processes
    C Risk symptoms
    D Potential risk events

    20 Puts into overall change control include all of the following except
    a Project plan
    B Change requests
    C Change control system
    D Performance reports

    21 Activity duration estimate inputs include all of the following except
    a Resource requirements
    B Basis of estimates
    C Activity lists
    D Constraints

    22 All of the following are contract types except
    a Unitprice
    B Makeorbuy
    C Cost reimbursable
    D Lump sum

    23 Initiation inputs for a project include all of the following except
    a Product description
    B Strategic plan
    C Project charter
    D Selection criteria

    24 Responses to risk threats include all of the following except
    a Avoidance
    B Acceptance
    C Mitigation
    D Rejection

    25 The process of performance reporting includes all of the following except _____________
    A Status reporting
    B Progress reporting
    C Forecasting
    D Product analysis

    26 Constrained optimization methods of project selection include
    a Scoring models
    B Benefitcost ratios
    C Multiobjective programming algorithms
    D Subjective analyses

    27 Which of the following statements concerning contract type is correct
    A A fixed price contract contains the most risk for the buyer
    B Cost reimbursable contracts offer sellers the highest profit potential
    C Lump sum contracts offer sellers the greatest profit potential
    D Unit price contracts are illegal in many jurisdictions

    28 A Work Breakdown Structure (WBS) numbering system should allow project staff to
    a Identify the level at which individual WBS elements are found
    B Identify configuration management milestones
    C Estimate the costs of WBS elements
    D Provide project justification

    29 All of the following are true quality statements except
    a Quality improvement depends upon better definition and increased awareness of the requirementsspecifications
    B Project quality management must address both management of the project and the product of the project
    C Recognition of key actions required of each team member is necessary to meet quality objectives
    D Computeraided design systems can improve quality but only at the expense of an increase in the cost of design

    30 All of the following are examples of tools often used in cost estimating except
    a Parametric modeling
    B Analogous estimating
    C Bottomup estimating
    D Activity duration estimates

    31 At XYZ Inc the hourly wage for semiskilled workers is 1400 The annual audit shows that fringe benefits cost 30 of basic wages and that overhead costs are 60 of wages plus fringe benefits What is the loaded hourly wage for a semiskilled worker at XYZ Inc
    A 2714
    B 2896
    C 3003
    D 2912

    32 Of the following estimates which most accurately reflect the actual cost of the project
    A Conceptual estimates
    B Order of magnitude estimates
    C Preliminary estimates
    D Bottomup estimates

    33 The most crucial time for project risk assessment is
    a When a problem surfaces
    B During the planning phase
    C During the closeout phase
    D After the project schedule has been published

    34 When there is uncertainty associated with one or more aspects of the project one of the first steps to take is to
    a Revise project plan
    B Conduct a riskbenefit analysis
    C Conduct a needs analysis
    D Increase the estimated cost of the project

    35 Including a contingency reserve in the project budget is intended to
    a Reduce the probability of scope changes
    B Increase the probability of scope changes
    C Reduce the probability of a cost overrun
    D Increase the probability of a cost overrun

    36 Given the information in the following table what is the expected value from this risk event
    Probability Result
    a 10000
    B 7500
    C + 2500
    D 7000

    37 A contractor is working on a fixed price contract that calls for a single lump sum payment upon satisfactory completion of the contract About halfway through the contract the contractor project manager informs their contract administrator that financial problems are making it difficult for them to pay their employees and subcontractors The contractor asks for a partial payment for work accomplished Which of the following actions by the buyer is most likely to cause problems for the project
    A Starting partial payments for work accomplished
    B Making no payments because it would violate the conditions of the contract
    C Paying for work accomplished to date
    D Negotiating a change to the payment conditions in the contract

    38 A precise description of a physical item procedure or service for implementation of an item or service is called :
    a Work package
    B Baseline
    C Product description
    D Work breakdown structure (WBS) element

    39 A project should be terminated for all of the following reasons except
    a Lack of team synergy
    B The project no longer meets the company's objectives
    C The resources are not available to complete project activities
    D Project funding has been significantly reduced

    40 One common way to compute estimated at completion (EAC) is to take the project budgetedatcompletion and
    a Divide it by the schedule performance index
    B Multiply it by the schedule performance index
    C Multiply it by the cost performance
    D Divide it by the cost performance index


    参考答案
    1B 2A 3C 4B 5C 6A 7A 8D 9B10B 11C 12D 13A 14D 15D 16A 17C 18D 19A 20C
    21B 22B 23C 24D 25D 26C 27C 28A 29D 30D 31D 32D 33B 34B 35C 36D 37B 38C 39A 40D

    文档香网(httpswwwxiangdangnet)户传

    《香当网》用户分享的内容,不代表《香当网》观点或立场,请自行判断内容的真实性和可靠性!
    该内容是文档的文本内容,更好的格式请下载文档

    下载文档到电脑,查找使用更方便

    文档的实际排版效果,会与网站的显示效果略有不同!!

    需要 2 积分 [ 获取积分 ]

    下载文档

    相关文档

    PMP考试模拟题(20个)

    Communications Sample Questions1. Which of the following is not a process of Project Communcati...

    8年前   
    449    0

    PMP考试模拟题(28个)

    Sample Professional Responsibility exam questions1.  While working on an external project your c...

    10年前   
    576    0

    PMP项目管理模拟考试卷——16-2004.模拟考试试题

    1. What are the 4 stages of team development?a. Assignment, kick-of, training, communicatingb. F...

    10年前   
    541    0

    PMP项目管理模拟考试卷——5-科兹纳PMP模拟试卷

    概述1、项目是一系列——的活动和任务。A、具有特定目标。B、具有明确开始和终止日期。C、资金有限(如果可用)。D、消耗资源。E、以上皆是。2、成功的项目管理可以被定义为——达到了项目管理目标。...

    12年前   
    950    0

    PMP项目管理模拟考试卷——17-成都模拟题

    1. To help the project team function more efficiently on complex and interrelated tasks, the pro...

    12年前   
    405    0

    PMP项目管理模拟考试卷——18-成都模拟题答案

    模拟题答案1C21C41D61C81C2C22D42D62B82A3B23D43B63A83A4A24B44D64A84B5A25B45C65C85B6B26A46A

    10年前   
    571    0

    PMP项目管理模拟考试卷——9-(IPMP)认证考核试题

    国际项目管理专业资质认证(IPMP)知识考核笔试试题 题号分数阅卷人一二三四五六七总分级 别: IPMA C级 考 点: ...

    10年前   
    602    0

    PMP项目管理模拟考试卷——22-IPMA C级试卷

    华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA C级 应试人员: 准考证号: 分...

    12年前   
    667    0

    PMP项目管理模拟考试卷——23-IPMA D级试卷

    华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA D级 应试人员: 准考证号: 分...

    12年前   
    981    0

    PMP考试学习心得

    PMP考试学习心得  我几乎都是利用自己的业余时间进行PMP和项目管理学习的,一般都在项目上很忙,时间时非常的宝贵的,我最初就是这样计划的,一定找一家让我省力气的、高效的培训班,这样我投入的精...

    12年前   
    407    0

    PMP考试的100个关键点

    1. 一个项目在启动阶段会进行量级估算,准确范围是-50至100%。2000版的量级估算准确度为:-25%到+75%。 参考:PMBOK2004 P161 CH P137 7.1 成本估算。 ...

    12年前   
    451    0

    2002年PMP考试的一些信息

              2002年PMP考试的一些信息一、2002年PMP考试日期表考试日期3月23日6月22日9月21日12月7日报名截止日期1月15日4月12日7月12日9月30日提交材料截止...

    14年前   
    437    0

    PMP考试技巧24计

    PMP考试技巧24计 第1计 先调查,后决策例1:在新公司,你发现公司的一些财物报告没有遵照会计准则,所以并不准确,在这种情况下,你首先要做的是? A、将公司不准确的记账操作通知政府B、与你...

    9年前   
    434    0

    PMP项目管理模拟考试卷——21-项目管理师模拟试卷

    项目管理师模拟试卷1、 单项选择题:(1) 确定项目范围的工具是:(C)A. PROJECT 2000;B. CPM;C. WBS;D. PERT;(2) 在项目管理过程中,自制-外购分析应用...

    12年前   
    660    0

    2019编导艺考模拟真题和2018考试真题

    2019 编导艺考模拟真题《我们诞生在中国》是一部()A.剧情片B.纪录片C.美术片D.科教片一般标准电影帧数为()A 24B 25C 48D 602016年10月17日7:30分,神舟十一号...

    4年前   
    2021    0

    2023年教师招聘考试填空题模拟试题及答案(2)

    1、 教育心理学是一门研究学校情境中 学与教 的基本心理规律的科学。 2 教育心理学是 应用心理学 的一种,是心理学与教育学的交叉学科。3、 所谓心理发展,是指个体从出生、成熟、衰老直...

    3个月前   
    97    0

    2023年小学教师招聘考试多项选择题模拟试题及答案

    1.教育活动的基本规律包括。A.教育与生产力之间的矛盾或关系B.教育与社会发展之间的矛盾或关系C.教育现象内部各要素之间的矛盾或关系D.教育与人的身心发展之间的矛盾或关系E.教育与生产关系之间的矛盾或关系

    3个月前   
    167    0

    2023年司法考试《法理学》不定项选择题模拟试题及答案

     1.依据宪法,下列哪个领导人或机关或组织必须向全国人民代表大会报告工作?  A.中华人民共和国主席  B.中央军委主席  C.全国人大常委会  D.中国人民政治协商会议  答案:C。  2.依...

    3个月前   
    174    0

    2023年小学教师招聘考试多项选择题模拟试题及答案

    1.教育活动的基本规律包括。A.教育与生产力之间的矛盾或关系B.教育与社会发展之间的矛盾或关系C.教育现象内部各要素之间的矛盾或关系D.教育与人的身心发展之间的矛盾或关系E.教育与生产关系之间的...

    3个月前   
    106    0

    PMP学习心得

    PMP学习心得  我参加的XX年1月的培训班,3月23日考试。成绩不算高但庆幸通过了,回顾整个学习,复习,考试各阶段,把自己的经验教训总结分享给各位同学。  01. 提前报名,课前通读一遍。 ...

    10年前   
    585    0

    文档贡献者

    h***9

    贡献于2012-04-18

    下载需要 2 积分 [ 获取积分 ]
    下载文档