a2o工艺污水处理厂毕业设计


    a2o工艺污水处理厂毕业设计
    目录
    摘 3
    Abstract 4
    第章 设计概 6
    11 设计务 6
    12 设计目 7
    第二章 工艺流程确定 8
    21 工艺流程较 8
    22 工艺流程选择 11
    第三章 工艺流程设计计算 13
    31 设计流量计算 13
    32 设备设计计算 13
    321 格栅 13
    322 提升泵房 14
    323 沉砂池 15
    324 初沉池 16
    325 A2O 17
    326 二沉池 23
    327 接触池加氯间 25
    328 污泥处理构筑物计算 26
    33 构建筑物设备览表 29
    第四章 面布置 31
    41 污水处理厂面布置 31
    411面布置原 31
    412具体面布置 33
    42污水处理厂高程布置 34
    421务 34
    422高程布置原 34
    423高程布置结果 35
    第五章 供电仪表供热系统设计 41
    51变配电系统 41
    52监测仪表设计 41
    第六章 劳动定员 42
    61定员原 42
    62污水厂数定员 42
    第七章 参考文献 43
    致谢 44
    英文原文文献 45


    作某开发区污水处理厂初步设计施工图设计该处理厂处理城市污水水质较复杂:
    五日生化需氧量(BOD5):140mgL
    悬浮物(SS):200mgL
    化学需氧量():260mgL
    NH3N:30mgL
    处理水质求
    BOD5≤20mgL
    SS≤20mgL
    ≤60mgL
    NH3N≤15mgL

    根设计求求新思想该污水处理工程进水中氮含量均偏高BOD5SS时需进行脱氮处理采代水处理工艺中较流行工艺工艺环境条件功微生物群落机配合加厌氧缺氧条件部分生物降解机物开环断链NP机碳时提高降解机物效果时完成机物硝化脱氮磷量摄取等功脱氮前提NH3-N应完全硝化氧池完成功缺氧池完成脱氮功厌氧池氧池联合完成磷功
    外该工艺具高效节特点耐击负荷较高出水水质更具广泛适应性完全适合设计实际求工艺构筑物包括格栅污水泵房流沉砂池氧池厌氧池缺氧池二沉池接触消毒池浓缩池污泥脱水机房等
    设计采体工艺工艺流程相简单省污泥消化系统节省基建投资运行费该工艺处理污水运行稳定易理出水水质达设计求真正做污水综合利
    关键词: 格栅 泵房 新工艺 二沉池

    Abstract

    It is a preliminary design and construction drawing for the sewage treatment plant development zone This plant treats municipal sewage mainly Its water quality is more complicated
    Suspended substance () 200mgL
    The biochemical oxygen demand of five days () 140mgL
    The chemical oxygen demand () 260mgL
    NH3N 30mgL
    Treated water quality is required
    ≤20mgL
    SS≤20mgL
    ≤60 mgL
    NH3N≤15mgL
    According to the designing requirement and thought of looking for novelty the content of nitrogen in the municipal sewage is on the high side in this project so while getting rid of and it should be treated with a proper process We adopt and use a kind of craft which is a comparatively popular craft at present named AnaerobicAnoxicOxic
    The advantage of this comprehensive craft is extensive adaptability totally suitable for reality originally designed purpose Its main structures includes gate well grid sewage pumping house earate and sinking sand pool oxidizing ditch the second sinking pool contacting pool concentration tank mud to dehydrate in the computer lab etc
    Process due to different environmental conditions different functions of microbial communities in the organic combined with anaerobic anoxic condition some nonbiodegradable organic matter can be open or broken chain making N P organic carbon is also removed and to enhance nondegradable organic removal It can simultaneously remove organic matter nitrification and denitrification excessive intake of phosphorus was removed and other functions provided that removal of NH3 N should be fully nitrification aerobic tank to complete the function oxygen tank is complete removal function Anaerobic tank and aerobic phosphorus removal capabilities to complete the joint pool
    This design have adopted the practical craft and equipment of good performance and the procedure is simple management is convenient do not need to add the first sinking pool digestive system reducing building and operating expenses realizing automation totally at the same time easy to manage making the treated water reach sewage discharge standard accomplish the rational utilization of water resource

    Keywords Grid Pumpraft The second sinking pool
    第章 设计概
    11 设计务
    (1)原始
    设计题目 6万m3d城镇污水推流式曝气池处理工程设计
    设计基础资料:
    原始数 Q60000m3d
    进水水质:BOD5140mgl COD200mgl
    SS200mgl NH3N30mgl
    出水水质:BOD5<20mgl COD<60mgl
    SS<20mgl NH3N<15mgl
    (2)设计容求
    设计容包括:
    1) 文献获取:充分利现文献资源获取充分国外相关文献
    2) 工艺方案选:文献认真阅读课题容进行酝酿思考确定设计方案
    3) 工艺构筑物计算:计算确定构筑物尺寸工艺流程运行参数
    4) 设计图纸:详见设计求
    5) 设计说明书编制:包括单元构筑物设计附属设备设计设备选型运行费投资估算
    6) 撰写文:毕业文求规范完成文
    (3)设计求
    1) 根设计务书提供资料相关标准规范进行该项目设计包括:学会查阅科技文献资料解城市污水处理技术国外现状发展趋势
    2) 查阅科技文献资料进行纳运写出文献综述
    3) 弄清设计思路掌握工艺设计程序进行该项目工艺设计包括:确定工艺流程设计计算编制说明书绘制工程设计图纸等实际成果求包括:
    ① 设计说明书(附400字摘48关键词中文摘应英文摘)
    ② 计算书
    ③ 设计图纸(6~8张):
    a 污水处理站总面布置设计图1张
    b 污水处理站高程布置图(兼做工艺流程图)1张
    c 单元处理构筑物工艺设计图纸35张
    d道系统图1~2张
    4) 毕业文撰写规范
    5) 文期间学学院求遵守项规定听老师指导
    12 设计目
    伴着国城乡济快速发展避免带种样环境问题环境污染生态破坏三废污染问题中水污染问题成重中重水生命源国严重缺水国家水资源分布衡南北少东西少均水资源占量世界均水面国水资源紧缺现状面国河流湖泊均程度受污染现状国推行系列旨节约水保护现水资源政策规模建设污水处理厂源头治理疑保护河流湖泊污染办法时污水处理厂处理污水中BOD5COD等污染物指标幅降排水符合国家规定会生态环境造成污染
    通城市污水处理厂处理工艺选择设计培养环境工程专业学生利学水污染控制理系统掌握污水处理方案较优化构筑物尺寸运行参数等进步深造学基础
    第二章 工艺流程确定
    21 工艺流程较
    城市污水处理厂方案考虑效BOD5适NP采SBR氧化沟法AAO法体化反应池三沟式氧化沟改良设计
    A SBR法
    工艺流程:
    污水 → 级处理→ 曝气池 → 处理水
    工作原理:
    1)流入工序:废水注入注满进行反应方式单纯注水曝气缓速搅拌三种
    2)曝气反应工序:污水注满开始曝气操作重工序根污水处理目P脱N应进行相应处理工作
    3)沉淀工艺:混合液泥水分离相二沉池
    4)排放工序:排曝气沉淀产生清液作处理水排放直低水位反应器残留部分活性污泥作种泥
    5)机工序:工处理水排放反应器处停滞状态等周期
    特点:
    ①数情况设置调节池心
    ②SVI值较低易沉淀般情况会产生污泥膨胀
    ③通运行方式调节进行磷脱氮反应
    ④动化程度较高
    ⑤时处理效果优连续式
    ⑥单方投资较少
    ⑦占规模处理水量较
    B 厌氧池+氧化沟
    工作流程:
    污水→中格栅→提升泵房→细格栅→沉砂池→厌氧池→氧化沟
    →二沉池→接触池→处理水排放
    工作原理:
    氧化沟般呈环形沟渠状污水沟渠作环形流动利独特水力流动特点沟渠转弯处设曝气装置曝气池方厌氧池方氧段产生富氧区缺氧区进行硝化反硝化作取脱氮效应时氧化沟法污泥龄较长存活世代时间较长微生物进行特反应磷脱氮
    工作特点:
    ①液态介完全混合推流间利活性污泥适生物凝聚作
    ②水量水温变化较强适应性处理水量较
    ③污泥龄较长般长达15-30天存活时间较长微生物果运行进行磷脱氮反应
    ④污泥产量低已达稳定
    ⑤动化程度较高理
    ⑥占面积较运行费低
    ⑦脱氮效果进步提高脱氮效果坏部分决定循环提高脱氮效果势必增加循环量氧化沟循环量政说受限制具更脱氮力
    ⑧氧化沟法问世应普遍技术资料丰富
    C AAO法
    优点:
    ①该工艺简单步脱氮磷工艺 总水力停留时间总产占面积少工艺
    ②厌氧氧交运行条件丝状菌量增殖污泥膨胀虞SVI值般均100
    ③污泥中含磷浓度高具高肥效
    ④运行中勿需投药两A段轻缓搅拌啬溶解氧浓度运行费低
    缺点:
    ①磷效果难行提高污泥增长定限度易提高特PBOD值高时更
    ②脱氮效果难进步提高循环量般2Q限宜太高否增加运行费
    ③沉淀池保持定浓度溶解氧减少停留时间防止产生厌氧状态污泥释放磷现象出现溶解 浓度宜高防止循环混合液缺反应器干扰
    D 体化反应池(体化氧化沟称合建式氧化沟)
    体化氧化沟集曝气沉淀泥水分离污泥回流功体需建造单独二沉池基运行方式体分六阶段(包括两程)
    阶段A:污水通配水闸门进入第沟沟出水堰动调节关闭沟转刷低转速运转仅维持沟污泥悬浮状态环流供氧量足系统处缺氧状态反硝化菌阶段产生硝态氮原成氮气逸出程中原生污水作碳源进入第沟污泥污水混合液环流进入第二沟第二沟转刷整阶段均高速运行污水污泥混合液沟保持恒定环流转刷供氧量足氧化机物氨氮转化成硝态氮处理污水活性污泥起进入第三沟第三沟沟转刷处闲置状态时第三沟仅作沉淀池泥水分离处理出水通已降低出水堰第三沟排出
    阶段B:污水入流第沟调入第二沟第沟转刷开始高速运转开始沟处缺氧状态着供氧量增加逐步成富氧状态第二沟处理污水活性污泥起进入第三沟第三沟作沉淀池沉淀污水通第三沟出水堰排出
    阶段C:第沟转刷停止运转开始泥水分离需设渡段约时该阶段末分离程结束C阶段入流污水然进入第二沟处理污水然通第三沟出水堰排出
    阶段D:污水入流第二沟调第三沟第沟出水堰开 第三沟出水堰关停止出水时 第三沟转刷开始低转速运转污水污泥起流入第二沟第二沟曝气流入第沟时第沟作沉淀池阶段D阶段A相类似反硝化作发生第三沟处理污水通第沟已降低出水堰排出
    阶段E:污水入流第三沟转第二沟第三沟转刷开始高速运转保证该段末沟硝化阶段第沟作沉淀池处理污水通该沟出水堰排出阶段E阶段B类似两外沟功相反
    阶段F:该阶段基C阶段相第三沟转刷停止运转开始泥水分离入流污水然进入第二沟处理污水第沟出水堰排出
    特点:
    ①工艺流程短构筑物设备少设初沉池调节池单独二沉池污泥动回流投资省耗低占少理简便
    ②处理效果稳定BOD5SS率均90%95%更高COD率85%硝化脱氮作明显
    ③产生剩余污泥量少污泥需孩性质稳定易脱水会带二次污染
    ④造价低建造快设备事率低运行理费少
    ⑤固液分离效率般二沉池高池容整系统较流量浓度范围稳定运行
    ⑥污泥回流时减少污泥膨胀
    种氧生物处理工艺方法技术济指标较

    种氧生物处理工艺方法技术济指标较
    方案
    技术指标
    (BOD5
    率%)
    济指标*
    运行情况

    基建费


    运行
    稳定

    情况
    适应负
    荷波动
    备注
    传统活性
    污泥法
    85~95
    100
    100
    100


    适应
    适中等浓度生
    活污水工业废水击敏感
    渐减曝气法
    85~95
    100
    100
    100



    空气供应逐渐减配合
    机负荷需
    分段曝气法
    85~95
    100
    100
    100



    处理污水范围较广
    完全混合法
    85~90
    <100
    <100
    >100
    稳定
    简便
    适应

    抗击负荷
    浅层曝气法
    85~91
    <100
    <100
    >100
    稳定
    简便

    适中型规模污水厂
    深层曝气法
    85~95
    >100
    <100
    <100
    稳定
    简便
    适应
    适中型规模污水厂
    深井曝气法
    85~90
    >100
    <100
    <100
    稳定

    适应
    施工难度般
    吸附生法
    80~90
    <100
    >100
    <100

    简便

    适高悬浮固体污水
    纯氧曝气法
    85~95
    >100
    >100
    <100

    麻烦
    适应
    般应空间较
    济氧源方
    氧化沟
    90~95
    <100
    >100
    >100
    稳定
    简便
    适应
    适中型污水厂
    需脱氮磷区
    SBR
    90~99
    <100
    100
    <100
    稳定
    简便
    适应
    适中型污水处理厂
    AB 法
    85~95
    <100
    <100
    约100

    简便
    适应
    分期建设达
    水质求
    AOA2O
    90~95
    >100
    >100
    >100



    需脱氮磷型污水厂
    生物膜法
    >90
    <100
    <100
    约100
    稳定
    简便
    适应
    适型污水厂
    22 工艺流程选择
    项目污水处理特点:①污水机污染BODCOD 075生化性较重金属难生物降解毒害污染物般超标②污水中污染物指标BODCODSS值典型城市污水值
    针特点出水求现城市污水处理技术特点采生化处理济求出水回处理工艺尚应硝化考虑NH3N出水浓度排放求较低必完全脱氮根国外已运行中型污水处理厂调查达确定治理目标采A2O活性污泥法
    具体工艺流程:
    进水
    格栅
    提升泵房
    沉砂池
    砂水分离

    初沉池
    厌氧池
    缺氧池
    氧池
    二沉池
    接触池
    排放
    消毒剂
    初沉污泥
    泵房
    浓缩池
    贮泥池
    脱水间
    泥饼








    第三章 工艺流程设计计算
    31 设计流量计算
    均流量:60000td≈60000m3d2500 m3h0694 m3s

    总变化系数: (-均流量Ls)

    设计流量:
    131×6000078600 m3d3275 m3h09097 m3s

    32 设备设计计算
    321 格栅
    格栅组行金属栅条筛网制成安装污水渠道泵房集水井进口处污水处理厂端部截留较悬浮物漂浮物般情况分粗细两道格栅
    格栅型号:链条式机械格栅
    设计流量
    栅前流速栅流速
    栅前部分长度05m格栅倾角单位栅渣量
    (1) 确定栅前水深

    (2) 栅前间隙数(取58)
    (3) 栅条效宽度
    (4) 设水渠渐宽部分展开角
    进水渠渐宽部分长度
    (5) 格栅出水渠道渐宽部分长度
    (6) 栅水头损失取栅前渠道超高部分
    栅前槽总高度
    栅总高度
    (7) 格栅总长度

    265m
    (8) 日栅渣量

    宜采机械清渣
    322 提升泵房
    1水泵选择
    设计水量78600m3d选择4台潜污泵(31备)

    需扬程60m
    选择350QZ100型轴流式潜水电泵
    扬程m
    流量(m3h)
    转速(rmin)
    轴功率kw
    叶轮直径mm
    效率
    722
    1210
    1450
    299
    300
    795
    2集水池
    (1)容积 台泵流量时6min出流量设计集水池效容积

    (2)面积 取效水深面积

    (3)泵位安装
    潜水电泵直接置集水池电泵检修采移动吊架
    323 沉砂池
    沉砂池作污水中砂子煤渣等重较颗粒保证续处理构筑物正常运行
    选型:流式沉砂池
    设计参数:
    设计流量设计水力停留时间t40s
    水流速v025ms
    (1) 长度:
    (2) 水流断面面积:
    (3) 池总宽度:效水深
    (4) 沉砂斗容积:
    T=2dX=30m3106m3

    (5) 沉砂斗容积()
    设分格2格沉砂斗

    (6) 沉砂斗部分尺寸:
    设贮砂斗底宽b1=05m斗壁水面倾角60°贮砂斗高h’3=10m

    (7) 贮砂斗容积:(V1)
    >
    符合求
    (8) 沉砂室高度:(h3)
    设采重力排砂池底坡度i=6%坡砂斗

    (9) 池总高度:(H)
    设超高
    (10) 核算流速

    324 初沉池
    初沉池作室污水仲密度固体悬浮物进行沉淀分离
    选型:流式沉淀池
    设计参数:
    (1) 池子总面积A表明负荷取


    (2) 沉淀部分效水深h2

    (3) 沉淀部分效容积

    (4) 池长L

    (5) 池子总宽度B

    (6) 池子数宽度取5m

    (7) 校核长宽
    (符合求)
    (8) 污泥部分需总容积V
    已知进水SS浓度200mgL
    初沉池效率设计50%出水SS浓度
    设污泥含水率97%两次排泥时间间隔T2d污泥容重

    (9) 格池污泥需容积

    (10) 污泥斗容积V1

    (11) 污泥斗梯形部分污泥容积V2



    (12) 污泥斗梯形部分容积

    (13) 沉淀池总高度H

    325 A2O
    设计参数
    1设计流量 Q60000m3d
    2设计进水水质 COD260mgLBOD5(S0)140mgLSS200mgLNH3N30mgL
    3设计出水水质 COD60mgLBOD5(Se)20mgLSS20mgLNH3N15mgL
    4设计计算采A2O生物磷工艺
    (1) BOD5污泥负荷
    (2) 回流污泥浓度XR6 000mgL
    (3) 污泥回流R100
    (4) 混合液悬浮固体浓度
    (5) 反应池容积V


    (6) 反应池总水力停留时间

    (7) 段水力停留时间容积
    厌氧:缺氧:氧=1:1:3
    厌氧池水力停留时间池容
    缺氧池水力停留时间池容
    氧池水力停留时间池容
    (8) 反应池尺寸
    反应池总容积
    设反应池2组单组池容
    效水深h50m
    单组效面积
    采5廊道式推流式反应池廊道宽
    单组反应池长度
    校核: (满足)
    (满足)
    取超高10m反应池总高
    (9) 反应池进出水系统计算
    (1)进水
    单组反应池进水设计流量
    道流速
    道水断面面积

    取出水径DN800mm
    校核道流速
    (2)回流污泥渠道单组反应池回流污泥渠道设计流量QR

    渠道流速
    取回流污泥径DN800mm
    (3)进水井
    反应池进水孔尺寸:
    进水孔流量:
    孔口流速
    孔口水断面积
    孔口尺寸取
    进水竖井面尺寸
    (4)出水堰出水竖井矩形堰流量公式


    式中 ——堰宽
    H——堰水头高m

    出水孔流量
    孔口流速
    孔口水断面积
    孔口尺寸取
    进水竖井面尺寸
    (5)出水单组反应池出水设计流量

    道流速
    道水断面积

    取出水径DN1100mm
    校核道流速
    (10) 曝气系统设计计算
    (1)设计需氧量
    中:第项合成污泥需量第二项活性污泥源呼吸需量第三项消化污泥需氧量第四项反硝化污泥需氧量
    (2)氨氮中氧化90参反硝化程10氮存
    (3)原

    (4)取

    +
    +

    48096+5502+1620414115176
    总需氧量1151764799
    需量均需氧量14

    1kgBOD5需氧量
    (5)标准需氧量
    采鼓风曝气微孔曝气器曝气器敷设池底距池底02m淹没深度38m氧转移效率EA=20%计算温度T25℃
    相应标准需氧量

    时供气量
    (6)需空气压力p

    式中



    (7)曝气器数量计算(单组反应池计算)
    供氧力计算需曝气器数量

    供风道计算
    供风干道采环状布置
    流量
    流速

    取干径DN600mm单侧供气(单侧廊道供气)支

    流速

    取支径DN400mm
    双侧供气
    流速

    取支径DN500mm
    (11) 厌氧池设备选择(单组反应池计算) 厌氧池设导流墙厌氧池分成3格格设潜水搅拌机1台需功率池容计算
    厌氧池效容积
    混合全池污水需功率
    污泥回流设备
    污泥回流
    回流污泥量
    设混合液回流泵房2座座泵房设3台潜污泵(21备)
    单泵流量
    水泵扬程根竖流程确定
    (12) 混合液回流设备
    (1)混合液回流
    混合液回流量
    设混合液回流泵房2座座泵房设3台潜污泵(21备)
    单泵流量
    (2)混合液回流
    混合液回流设计
    泵房进水设计流速采
    道水断面积


    取泵房进水径DN1000mm

    校核道流速:
    (3)泵房压力出水总设计流量
    设计流速采
    道水断面积

    取泵房压力出水径DN900mm

    326 二沉池
    设计参数
    沉淀池水流更稳进出水配水更均匀存排泥更方便常采圆形辐流式二沉池二沉池中心进水周边出水幅流式沉淀池2座二沉池面积表面负荷法计算水力停留时间t25h表面负荷15m3(m2•h1)
    (1) 池体实际计算
    (1)二沉池表面面积


    (2)池体效水深
    (3)混合液浓度回流污泥浓度
    保证污泥回流浓度二沉池存泥时间宜2h
    二沉池污泥区需存泥容积

    采机械刮吸泥机连续排泥设泥斗高度H205m
    (4)二沉池缓区高度H305m超高H403m沉淀池坡度落差H5063m
    二沉池边总高度
    (5) 校核径深
    二沉池直径水深

    (2) 进水系统计算
    (1)进水计算
    单池设计污水流量
    进水设计流量
    选取径DN1200mm

    (2)进水竖井
    进水竖井采D215m流速01~02ms
    出水口尺寸05×15m²6井壁均匀分布
    出水口流速
    (3)稳流筒计算
    取筒中流速
    稳流筒流面积
    稳流筒直径

    (4)出水部分设计
    单池设计流量
    环形集水槽流量
    采周边集水槽单侧进水池总出水口安全系数k取12
    集水槽宽度取b05米
    集水槽起点水深
    集水槽终点水深
    槽深取07m采双侧集水环形集水槽计算取槽宽b08m槽中流速
    设计取环形槽水深06m集水槽总高06+03(超高)09m采90°三角堰
    出水溢流堰设计
    采出水三角堰(90°)堰水头(三角口底部游水面高度)H1005m(H2O)
    三角堰流量
    三角堰数
    三角堰中心距(单侧进水)

    (4) 排泥部分设计
    (1)单池污泥量
    总污泥量回流污泥量加剩余污泥量
    回流污泥量
    剩余污泥量


    (2)集泥槽整池径两边集泥
    设计泥量
    集泥槽宽取b05m
    起点泥深
    终点泥深

    327 接触池加氯间
    采隔板式接触反应池
    1 设计参数
    设计流量:
    水力停留时间:
    设计投氯量:
    均水深:
    隔板间隔:



    2 设计计算
    (1)座接触池容积:
    表面积
    隔板数采2
    廊道总宽
    接触池长度
    长宽
    实际消毒池容积
    实际水深
    径校核均满足效停留时间

    (2)加氯量计算:
    设计加氯量
    选3台REGAL2100型负压加氯机(21备)单台加氯量10kgh
    328 污泥处理构筑物计算
    (1)回流污泥泵房
    二沉池活性污泥吸泥吸入池中心落泥排泥排入池外套筒阀井中然道输送回流泵房污泥刮泥板刮入污泥井中排泥排入剩余污泥泵房集泥井中
    设计回流污泥量QRRQ污泥回流R50%-100%考虑

    回流污泥泵设计选型:
    (1)扬程:
    设二沉池水面相面标高05m套筒阀井泥面相标高03m回流污泥泵房泥面相标高06m生物处理构筑物水面相标高15m污泥回流泵需提升高度21m
    (2)流量:
    泵房回流污泥量
    (3)选泵:
    选LXB900螺旋泵6台(51备)单台提升力480m3h提升高度20m-25m电动机转速n48rmin功率N55kW
    (2)剩余污泥泵房
    (1)设计说明
    二沉池产生剩余活性污泥处理构筑物排出污泥道流入集泥井剩余污泥泵(式)提升污泥浓缩池中
    (2)选泵:选1PN污泥泵Q7216 H1214mN3kW
    (3)污泥浓缩池
    采两座幅流式圆形重力连续式污泥浓缩池带栅条刮泥机刮泥采静压排泥剩余污泥泵房污泥送浓缩池
    1 设计参数
    设计流量
    进泥浓度:6gL
    初层池污泥含水率95
    污泥含水率99浓缩含水率97
    贮泥池出口污泥含水率92
    浓缩时间T20h浓缩池固体通量
    2 浓缩池尺寸
    面积:
    直径:
    高度:工作高度
    取超高缓层高度
    总高度
    浓缩污泥流量
    (4)贮泥池
    污泥量
    浓缩污泥量8533 含水率97
    初沉污泥量350 含水率95
    污泥量
    贮泥池容积
    设贮泥时间4h贮泥池容积

    贮泥池尺寸
    取池深H4m贮泥池面积
    设计圆形贮泥池座直径D54m
    搅拌设备
    防止污泥贮泥池终沉淀贮泥池设置搅拌设备设置液搅拌机1台功率10kw

    (5) 脱水间
    压滤机选型:滤流量
    设计2台压滤机台天工作7h台压滤机处理量
    选择DY15型带式压滤脱水机
    加药量计算
    设计流量
    絮凝剂PAM
    投加量干固体04计

    33 构建筑物设备览表
    序号
    名称
    规格
    数量
    设计参数
    设备



    1



    格栅


    L×B
    265m×173m



    1座
    设计流量
    60000m3d
    栅条间隙
    栅前水深
    栅流速
    HG1200回旋式机械格栅1套
    超声波水位计2套
    螺旋压榨机(Φ300)1台
    螺纹输送机(Φ300)1台
    钢闸门(20X17m)4扇
    手动启闭机(5t)4台


    2


    进水泵房

    L × B
    20m× 13m


    1座
    设计流量Q3215 m3h
    单泵流量Q 350m3h
    设计扬程H6mH2O
    选泵扬程H 722mH2O
    1mH2O9800 Pa
    螺旋泵(Φ1500mmN60kw)5台41备
    钢闸门(20mX20m)5扇
    手动启闭机(5t)5台
    手动单梁悬挂式起重机(2tLk4m)1台


    3

    流沉砂池

    L×B×H
    10m×46m×23m


    1座
    设计流量
    Q=3275 m3h
    水流速v 025 ms
    效水深H1 08m
    停留时间T 40S


    砂水分离器(Φ05m)2台


    4


    流式初沉池

    L×B×H
    216m×758m×8m


    13座

    设计流量Q 3275 m3h
    表面负荷q 20m3(m2·h)
    停留时间T 20 d


    全桥式刮吸泥机(桥长40m线速度3mmin N055X2kW) 2台
    撇渣斗4



    5


    曝气池


    L×B×H
    70m×55m×45m


    1座

    BOD150初沉池处理降低25
    罗茨鼓风机(TSO150Qa159m3min P196kPaN11kw)3台
    消声器6


    6


    辐流式二沉池


    D×H
    Φ326m×375m


    2座
    设计流量Q 2500m3h
    表面负荷q 15m3(m2·h)
    固体负荷
    停留时间T 25 h
    池边水深H12 m


    全桥式刮吸泥机(桥长40m线速度3mmin N055X2kW) 2台
    撇渣斗4
    出水堰板1520mX20m
    导流群板560mX06m

    7
    接触消毒池
    L×B×H
    324m×36m×3m

    1座
    设计流量Q3275 m3h
    停留时间T 05 h
    效水深H12 m

    注水泵(Q3~6 m3h )2台


    9


    加氯间


    L×B
    12m×9m


    1座

    投氯量 300 kgd
    氯库贮氯量15d计

    负压加氯机(GEGAL2100)3台
    电动单梁悬挂起重机(20t)1台



    10

    回流剩
    余污泥泵房(合建式)



    L×B
    10m×5m



    1座

    堵塞潜水式回流污泥泵2台
    钢闸门(20X20m)2扇
    手动单梁悬挂式起重机(2t)1台
    套筒阀DN800mm Φ1500mm 2
    电动启闭机(10t)2台
    手动启闭机(50t)2台
    堵塞潜水式剩余污泥泵3台


    第四章 面布置
    污水处理厂厂区处理单元构筑物连通处理构筑物间渠极线辅助性建筑物道路绿等污水处理厂厂区种工程设施进行合理面规划
    41 污水处理厂面布置
    污水处理厂面布置包括:生产性处理构筑物泵房鼓风机房药剂间化验室等辅助性建筑物种线等布置厂区道路系统室外明系统美化绿设施根处理厂规模般采例尺形图绘制总面图常例尺
    411面布置原
    1污水厂厂区面积应项目总规模控制作出分期建设安排合理确定期规模期工程投入运行年水量宜达期设计规模60%
    2污水厂总体布置应根厂建筑物构筑物功流程求结合厂址形气候质条件优化运行成便施工维护理等素技术济较确定
    3污水厂厂区建筑物造型应简洁美观节省材料选材适应建筑物构筑物群体效果周围环境协调
    4生产理建筑物生活设施宜集中布置位置应力求合理应处理构筑物保持定距离
    5污水污泥处理构筑物宜根情况分集中布置处理构筑物间距应紧凑合理符合国家现行防火规范求应满足构筑物施工设备安装埋设种道养护维修理求
    6污水厂工艺流程竖设计宜充分利形符合排水通畅降低耗衡土方求
    7厂区消防设计消化池贮气罐污泥气压缩机房污泥气发电机房污泥气燃烧装置污泥气道污泥干化装置污泥焚烧装置危险品仓库等位置设计应符合国家现行关防火规范求
    8污水厂根需适点设置堆放材料备件燃料废渣等物料停车场
    9污水厂应设置通构筑物附属建筑物必通道通道设计应符合列求:
    1) 车行道宽度:单车道35~40m双车道60~70m应回车道
    2) 车行道转弯半径宜60~100m
    3) 行道宽度宜15~20m
    4) 通高架构筑物扶梯倾角般宜采30°宜45°
    5) 天桥宽度宜10m
    6) 车道通道布置应符合国家现行关防火规范求应符合关部门规定
    10污水厂周围根现场条件应设置围墙高度宜20m
    11污水厂门尺寸应容运输设备部件车辆出入应设运输废渣侧门
    12污水厂联运行处理构筑物间应设均匀配水装置处理构筑物系统间宜设切换连通渠
    13污水厂种渠应全面安排避免相互干扰道复杂时宜设置廊处理构筑物间输水输泥输气线布置应渠长度短损失流行通畅易堵塞便清通污水处理构筑物间渠连通条件适宜时应采明渠
    廊宜敷设仪表电缆电信电缆电力电缆水污水污泥生水压缩空气等设置色标
    廊应设通风明广播电话火警燃气体报警系统独立排水系统吊物孔行通道出入口维护需设施等应符合国家现行关防火规范求
    14污水厂应合理布置处理构筑物超越渠
    15处理构筑物应设排空设施排出水应回流处理
    16污水厂宜设置生水处理系统
    17厂区水系统生水系统严禁处理装置直接连接
    18污水厂供电系统应二级负荷设计重污水厂宜级负荷设计满足述求时应设置备动力设施
    19污水厂附属建筑物组成面积应根污水厂规模工艺流程计算机监控系统水理体制等结合实际情况着节约原确定应符合现行关规定
    20位寒冷区污水处理构筑物应保温防冻措施
    21根维护理需宜厂区适点设置配电箱明联络电话洗水栓浴室厕等设施
    22处理构筑物应设置适栏杆防滑梯等安全措施高架处理构筑物应设置避雷设施
    412具体面布置
    1工艺流程布置
    工艺流程布置根设计务书提供面积形采直线型布置种布置方式生产联络线短水头损失理方便利日扩建
    2构(建)筑物面布置
    功污水处理厂布置分成三区域:
    1)污水处理区项污水处理设施组成呈直线型布置包括:污水总泵站格栅间流沉砂池初沉池沉淀池消毒池鼓风机房
    2)污泥处理区位厂区导风风污泥处理构筑物组成呈直线型布置包括:污泥浓缩池贮泥池等
    3)生活区该区办公室宿舍食堂锅炉房浴房等建筑物组合区
    位导风风
    3污水厂线布置
    污水厂线布置线布置:
    1)污水厂工艺道
    污水总泵站提升处理工艺处理构筑物排入水体
    2)污泥工艺道
    污泥剩余污泥工艺处理运出厂外
    3)厂区排水道
    厂区排水道系统包括构筑物清液溢流构筑物放空建筑物排水厂区雨水雨水水质达排放标准直接排放构筑物清液溢流构筑物放空建筑物排水污水污染物浓度高水质达排放标准直接排放设计中收集接入泵前集水池继续进行处理
    4)空气道
    5)超越道
    6)厂区该水道消火栓布置
    厂外接入送建筑物水点厂区隔1200m检间距设置1室外消火栓
    4厂区道路布置
    1)厂道路布置
    厂外道路厂办公楼连接带路厂道路道宽60m设双侧15m行道植树绿化
    2)车行道布置
    厂区构(建)筑物布置车行道道宽40m呈环状布置
    3)步行道布置
    物品器材运输建筑物设步行道厂道车行道相连
    5厂区绿化布置
    厂区方进行绿化
    42污水处理厂高程布置
    污水处理构筑物间通畅流动保证处理厂正常运行需进行高程布置确定构筑物连接高程
    降低运行费便维护理污水处理构筑物间流动已重力流考虑宜污泥利重力流动需提升时应量减少抽升次数保证污泥利流应精确计算处理构筑物间水头损失考虑扩建时预留储备水头
    421务
    污水处理厂污水处理流程高程布置务:
    1确定处理构筑物泵房标高
    2确定处理构筑物间连接渠尺寸标高
    3通计算确定部分水面标高够污水处理流程处理构筑物间畅通流动保证污水处理厂正常运行
    422高程布置原
    1保证污水构筑物间利流
    2认真计算道程损失局部损失处理构筑物计量设备联络渠水头损失考虑时流量雨天流量事时流量增加留定余应考虑某座构筑物停止运行时联运行余构筑物关连接渠通全部流量
    3考虑远期发展水量增加预留水头
    4选择条距离长水头损失流程进行水力计算
    5计算水头损失时般应期流量作构筑物渠设计流量计算涉远期流量渠设备时应远期流量设计流量酌加扩建时备水头
    6设置终点泵站污水厂水力计算常接受处理污水水体高水位作起点逆污水处理流程倒推计算防处理污水流出二泵站需扬程较运行费较低时应考虑挖土深度宜免土建投资增加施工困难
    7作高程布置时应该注意污水流程污泥流程配合量减少需提升污泥量
    8协调高程布置面布置关系做减少占利污水污泥输送利减少工程投资运行成
    423高程布置结果
    该污水处理厂出水排入市政排水总干终点泵站提升排入河流污水处理厂高程布置身素决定
    采普通活性污泥法辐流式二沉池曝气池初沉池占面积较果埋深设计方面利施工利土方衡量减少埋深降低土建工程投资考虑出水口水面高程定64m相应构筑物设施高程出水口逆流计算出水头损失算出
    高层布置计算程
    (1)简单计算程

    h1—程水头损失 h1 —坡度0005
    h2—局部水头损失 h2h1×50
    h3—构筑物水头损失

    a 巴氏计量槽
    H03m
    巴氏计量槽标高 17000m

    b 消毒池相标高
    排水口相标面标高: 000m
    消毒池水头损失: 030m
    消毒池相面标高: 14000m

    c 沉淀池高程损失计算
    l40m
    h1 0005×40020m
    h2 h1×50010m
    h3045m
    H2h1+h2+h3020+010+045075m
    沉淀池相面标高 06000m

    d A2O反应池高程损失计算
    l60m
    h1 0005×6003m
    h2 h1×50015m
    h3060m
    H3h1+h2+h306+015+030105m
    A2O反应池池相面标高 04625m

    e 流式沉砂池高程损失计算
    l10m
    h1 0005×10005m
    h2 h1×500025
    h303m
    H4h1+h2+h3005+0025+0300375m
    流式沉砂池相面标高 08525m

    f 细格栅高程损失计算
    h1 030m
    h2 h1×50015m
    h3030m
    H5h1+h2+h3030+015+030075m
    细格栅相面标高 16025m

    g 污水提升泵高程损失计算
    l8m
    h1 0005×8004m
    h2 h1×50002m
    h3020m
    H6h1+h2+h3004+02+020044m
    污水提升泵相面标高 41600m
    (2)详细计算程
    污水处理工程中简化计算般认水流均匀流渠水头损失程水头损失局部水头损失
    程水头损失式计算:

    式中 ——程水头损失
    ——段长度
    ——水力半径
    ——流速
    ——谢系数
    局部水头损失:
    式中 ——局部阻力系数
    (1)构筑物水头损失
    构筑物水头损失较计算起较烦琐设计中设计计算程中计算计算结果设计计算程中没计算验数值
    构筑物水头损失见表41
    表41 构筑物水头损失表
    构筑物名称
    水头损失(m)
    构筑物名称
    水头损失(m)
    中格栅
    014
    消毒池
    030
    细格栅
    075
    辐流沉淀池
    075
    流沉砂池
    038
    流接触池
    030
    污水提升泵房
    024
    巴氏计量槽
    03

    渠水力计算
    计量槽出水口突然扩突然缩局部阻力系数:0958+0101058
    接触池计量槽突然扩突然缩局部阻力系数:010+077087
    二沉池接触池突然扩突然缩两弯头局部阻力系数:
    集配水井二沉池突然扩突然缩局部阻力系数:048+09731453
    氧池集配水井突然扩弯头突然缩局部阻力系数:048+108+09732533
    缺氧池厌氧池两突然扩突然缩局部阻力系数取

    集配水井厌氧池突然扩弯头突然缩局部阻力系数:048+055+09732003
    沉砂池集配水井突然扩直角弯头突然缩局部阻力系数:048+105+09732503

    渠水力计算见表42
    表42 污水渠水力计算表
    渠构筑物名称
    流量

    渠设计参数
    水头损失

    (‰)



    局部
    合计
    出水口
    计量槽
    6947
    900
    205
    09
    150
    03075
    0138
    0307
    计量槽
    接触池
    6947
    900
    205
    09
    30
    0062
    0114
    0176
    接触池
    二沉池
    6947
    1000
    233
    09
    80
    0186
    0374
    0560
    二沉池
    集配水井
    6947
    1000
    233
    07
    50
    0017
    0152
    0169
    集配水井氧池
    6947
    1000
    200
    08
    50
    0100
    0268
    0368
    养池
    缺氧池
    6947
    1000
    200
    08
    20
    0040
    0307
    0347
    缺氧池
    集厌氧池
    6947
    800
    239
    08
    45
    0108
    0183
    0291
    集配水井初沉池
    6947
    800
    239
    10
    6
    0014
    0229
    0243

    (2)污泥道水头损失
    道程损失式计算:

    道局部损失计算:

    式中 ——污泥浓度系数
    ——污泥径
    ——流速
    ——道长度
    ——局部阻力系数
    查水排水设计手册知:污泥含水率97时污泥浓度系数71污泥含水率95时污泥浓度系数53
    连接道水头损失见表44
    表44 连接道水头损失
    渠构筑物名称
    流量
    渠设计参数
    水头损失()


    (‰)


    局部
    合计
    浓缩池贮泥池
    296
    200
    086
    68
    10
    0047
    0083
    0130
    贮泥池脱水机房
    296
    200
    086
    68
    10
    0047
    0083
    0130

    2污泥处理构筑物水头损失
    污泥重力流排出池体时污泥处理构筑物水头损失构筑物出流水头计算浓缩池般取15m二沉池般取12m
    3污泥高程布置
    面标高60m
    设计中污泥二沉池污泥浓缩池提升面重力流考虑脱水机房采面式(效容积面污泥斗设)污泥泥面标高60+3292m
    污泥高程布置计算表45

    表45 污泥高程布置计算表
    序号
    渠构筑物名称
    游泥面
    标高(m)
    游泥面
    标高(m)
    构筑物泥面标高(m)
    面标高
    (m)
    1
    脱水机房


    600
    600
    2
    贮泥池脱水机房
    605
    604

    600
    3
    贮泥池


    703
    600
    4
    浓缩池贮泥池
    606
    602

    600
    5
    浓缩池


    600
    600

    第五章 供电仪表供热系统设计
    51变配电系统
    1全厂变配电采10千伏双电源供电380伏变配电系统
    2污水泵回流污泥泵房控制
    3变配电间低压电瓶设紧急钮污水泵水位动停车
    4变配电间邻接触220伏明电源
    52监测仪表设计
    521设计原
    (1)污水污泥两部分分集中设置显示记录仪污水部分设置单独仪表
    间污泥记录仪设污泥泵房
    (2)根目前国监测仪表情况选定物力参量化学参量均采DDZⅡ型监测仪表
    (3)仪表动控制设计掌握适设计标准工程实效前提考虑技术先进性
    522监测容
    (1)污水泵房:集水池液位应集中显示设限报警
    (2)沉砂池:水温指示记录PH值指示记录
    (3)沉砂池:水温指示记录PH
    (4)A20处理设施:水温DO监测仪PH值回流污泥量
    (5)二沉池:水温指示记录PH
    (6)接触池:水温指示记录PH指示记录DO指示记录
    (7)浓缩池:泥温泥位指示记录设限报警PH指示记录
    (8)污泥脱水机房:污泥流量指示记录加药量指示记录
    523供热系统设计
    设计污水厂处华北区冬季应考虑采暖问题供热范围:综合楼职工娱乐室食堂中控室加氯间加药间等供热方式选暖气室装散热片

    第六章 劳动定员
    61定员原
    劳动定员试行规范规定:日处理量5—10万吨城市二级污水处理厂职工定员50日处理量5吨职工数位20—30(包括理员干部)占全厂数70
    62污水厂数定员
    污水处理厂员包括生产员生产辅助员理员生产员指直接参加生产员般包括运转工机修工电工加药工等生产辅助员指非直接参加生产员维修化验司机瓦工绿化食堂浴室工作员等理员指团工会行政技术调度财会员等
    设计污水厂污水量6万吨采职工数60理员干部12站20工45占753占5
    第七章 参考文献
    [1] 张杰排水工程北京:中国建筑工业出版社2000
    [2] 李圭白 张杰水质工程学北京:中国建筑工业出版社2006
    [3] 中国市政工程西南设计研究院编:水排水设计手册第1册北京:中国建筑工业出版社2001
    [4] 北京市市政工程设计研究院编:水排水设计手册第5册北京:中国建筑工业出版社2001
    [5] 中国市政工程西北设计研究院编:水排水设计手册第10册北京:中国建筑工业出版社2001
    [6] 中国市政工程华北设计研究院编:水排水设计手册第11册北京:中国建筑工业出版社2001
    [7] 张智水排水工程毕业设计(文)指南北京:水利水电出版社2000
    [8] 韩洪军水处理工程设计计算北京:中国建筑工业出版社2006
    [9] 尹士君李亚水处理构筑物设计计算北京:化学工业出版社2007
    [10] 邰生霞乔庆云水排水工程设计实践教程机械工业出版社2007
    [11] 室外排水设计规范GB50014-2006
    [12] 水排水制图标准GBT 501062001中华民国建设部2002
    [13] 城镇污水处理厂污染物排放标准GB18918-2002
    [14] 面水环境质量标准GB3838-2002
    [15] 中华民国环境保护法
    [16] GB3838-2002面水环境质量标准
    [17] GB50335-2002污水生利工程设计规范
    [18] GJ3189城镇污水处理厂附属建筑附属设备设计标准
    [19] GB1455493恶臭污染物排放标准
    [20] DBJ082391污水泵站设计规范
    [21] GB897896污水综合排放标准

    致谢
    月毕业设计生活中老师学予帮助表示衷心感谢
    首先感谢XX耐心指导悉心关怀留深刻印象予设计指导时老师科学思考方法严谨治学态度受益匪浅终生难忘衷心祝愿老师家庭美身体健康万事意培养出更更学生
    次感谢三年予教育老师专业课项基础知识深入解知识充实专业产生浓厚兴趣日工作充满希信心尤门专业基础课专业课更深认识学帮助坚强基础更事专业工作树立信心次衷心感谢课教师
    次感谢指导设计位老师教会知识时教会做道理严谨治学作风受益非浅伴生衷心祝愿动力工程学院位老师身体健康事业成桃李难天
    感谢学日常学生活中予帮助帮度难关点点滴滴见真情学朋友祝早日飞黄腾达展宏图祝愿位学够工作中南师动院争光添彩
    感谢帮助
    爱学爱老师爱学然学结束感惆怅学中知识仅仅书更做道理感谢老师学美丽校园予快乐会努力腔热血奋斗建设国家美丽校园增光添彩辜负老师厚
    祝福美丽校园明天会更







    英文原文文献
    Oxidize the ditch craft in dirty water handle of application and development
    Summary This text expatiated primarily the Carrousel oxidizes the construction craft mechanism of the ditch and circulate the problem exsited in the process with the homologous the method of solutionFinally introduce the Carrousel oxidize the latest research progress of the ditch and pointed out the future and main research
    direction
    Key phrase The Carrousel oxidizes the ditch divideds by the phosphor takes off the nitrogen construction mechanism
    Application and Development of Carrousel Oxidation Ditch Process on Wastewater Treatment
    Abstract The structure and the techniques of carrousel oxidation ditch process on nitrogen and phosphor removal are introduced in this paper The problems
    inrunning and their corresponding resolvent are also pointed At last The authorshowed the up to date research improvement and the mainly future research direction
    Key words Carrousel oxidation ditch nitrogen and phosphor removal structuretechniques
    1 Foreword
    Oxidize the ditch( oxidation ditch) again a continuous circulation spirit pond( Continuous loop reactor) is a live and dirty mire method a kind of to transformOxidizing the dirty water in ditch handles the craft be researched to manufacture by the hygiene engineering graduate school of Holland in the 50's of 20 centuries successSince in 1954 at Dutch throw in the usage for the very first timeBecause its a water fluid matter good circulate the stability and manage convenience etc technique characteristics already at domestic and international and extensive application in live the dirty water to is dirty to manage aqueously with the industry[1]
    Current application than oxidize extensively the ditch type includeThe ( Pasveer) oxidizes the ditch the ( Carrousel) oxidizes the ditch ( Orbal) oxidizes the ditch the type of T oxidizes the ditch( three ditch types oxidize the ditch) the type of DE oxidizes the ditch to turn to oxidize the ditch with the integral wholeThese oxidize the ditch because of the difference of esse in construction with circulating therefore each characteristics[2]This text will introduce construction mechanism existent problem and its latest developments that Carrousel oxidize ditches primarily
    2 The Carrousel oxidizes the construction of the ditch
    The Carrousel oxidize the ditch to be researched to manufacture by Dutch DHV company development in 1967Oxidize the last the company of DHV in foundation of the ditch in the original Carrousel to permited specially the company EIMCO to invent again with its patent in the United States Carrousel 2000 system( see the figure ) realizes the living creature of the higher request takes off the nitrogen with divided by the function of There has been in the world up to now more than 850 Carrousels oxidize the ditch with the Carrousel 2000 system are circulating[3]
    From diagram therefore the Carrousel oxidizes the ditch the usage the spirit of that definite direction control with shake up the device face to mix with the liquid deliver the level speed from but make drive the liquid of admixture that shake up is in oxidize ditch shut match outlet circulate flowTherefore oxidize the ditch have the special hydraulics flows the current complete mix with the characteristics of the type reactor have the characteristics that push the flow type reactor again the ditch inside exsits obviously of deliquescence oxygen density steps degreeOxidizing the ditch cross section is rectangle or trapezoids the flat surface shape is many for oval the ditch internal water is deep general for 25 ~ 45 m the breadth is deep compare for 21 also have the deep water amount to 7 ms of ditch inside average speed in water current is 03 ms sOxidize ditch spirit admixture equipments contain surface spirit machine the spirit of turn to brush or turn the dish and shoot to flow the spirit machine pipe type spirit machine with promote take care of type spirit machine etc match with in recent years usage still contain underwater push machine[4~6]
    3 The Carrousel oxidizes the mechanism of the ditch
    31 The Carrousel oxidizes the ditch handles dirty and aqueous principle
    The at the beginning
    common Carrousel oxidizes the dirty water in inside in craft of the ditch direct with dirty mire in reflux together enter oxidize the ditch systemThe surface spirit machine makes fuse in the liquid of admixture the density of the oxygen DO increases about 2 the 3 mgs LUnder this kind of well the term of the oxygen the microorganism gets the enough deliquescence oxygen comes and go to divided by the BODAt the same time the ammonia
    were too oxidized nitrate with second nitrate this time mix with the liquid be placed in the oxygen appearanceIn the spirit machine downstream after water current be become by the swift flow appearance of the spirit District of even flow the appearance the water current maintains in the minimum current velocity guaranteeing the live and dirty mire be placed in the floats the appearance( average current velocity>03 ms s)Oxidize microbially the process consumed to fuse the oxygen in the water until the value of DO declines for zero mixing with the liquid report the anoxia appearanceVersa nitric that turn the function through anoxia area mix with the liquid enter to have the oxygen area completing once circulatingThat system inside the BOD declines the solution is a continuous process the nitric turns the function to turn with the versa nitric the function take place in same pondBecause of structural restrict this kind of oxidize the ditch although can then valid whereabouts BOD divided by the phosphorus take off the nitrogenous ability limited[7]
    For the sake of the acquisition better divided by the phosphorus take off the nitrogenous result Carrousel 2000 systems increased a oxygen District before common Carrousel oxidize ditch with the unique oxygen area( call again that the versa nitric in front turns the area)The dirty mire in all refluxes enters the anaerobic District with 1030 dirty water can under the anoxia with 1030 carbon source term complete remaining of dirty mire in reflux inside nitric acid nitrogen to versa nitric to turn creates for the unique oxygen pond of hereafter unique oxygen termAt the same time anaerobic District inside of concurrently the sex germs convert the dissolubility BOD VFA the germ acquire the VFA its assimilation PHB the energy source needed solves in the phosphoric water and cause phosphatic releasingThe anaerobic District a water enters the inner part installs the unique oxygen area that have the mixer the socalled unique oxygen is a pond inside to mix with

    liquid since have no the numerator oxygen also have no the compound oxygen( nitric acid root) the here unique oxygen environment is n ext7090 dirty water can provide the enough carbon source can make the germ of released the phosphorus wellThe unique oxygen area connects behind the common Carrousel oxidizes the ditch system further completing to do away with the BOD and take off the nitrogen with divided by the phosphorus Finally mix with the liquid transfer the dirty mire inside in oxidize ditch enrich oxygen area eject while enriching the oxygen environment germ surfeit phosphorus from the water ejecting the system with the dirty mire in surplusLike this in Carrousel 2000 systems than completed to do away with the BOD COD with take off at the same time goodly the nitrogen divided by the phosphorus Synthesizing and
    Dirty water in the river City long sand City decontamination center[s of the dirty the factory of water in the first in Kunming of adoption that crafts handles the movement result of the factory thereforeThrough Carrousel 2000 system after handling the BOD COD SS does away with the rate to all come to a 90 above the TN does away with the rate comes to a 80 the TP does away with the rate to also come to a 90
    32 The Carrousel oxidizes the ditch divideds by the phosphorus takes off the nitrogenous influence factor
    Affecting the Carrousel oxidizes the ditch divideds by the phosphoric factor is dirty mire nitrate density and quality densities primarilyThe research expresses being total and dirty mire as 11 that a hour biggest phosphorus 4 with deal is its fuck dirty mire deal within live and dirty mire keep for the the germ physical endowment measures but when dirty mire over 15 d hour dirty mire the inside is biggest to contain the obvious descent in deal in phosphorus canning not reach the biggest divideding by the result of phosphorus on the contraryTherefore prolong persistently
    the dirty mire ( for example 20ds25ds30ds) is to have no necessary proper choose to use within the scope of 8~15 dAt the same time high nitrate density with low quality density disadvantage in divided by the process of phosphorus
    Affecting the Carrousel oxidizes the ditch takes off the nitrogenous and main factor is DO nitrate density and carbon source densitiesThe research expresses oxidizing the ditch inside exsits deliquescence oxygen density steps degree namely the good oxygen area DO attains 3~35 mgs L the anoxia area DO attains 0~05 mgs L is a prior condition to take place nitric turn reaction and versa nitrics turn the reactionAt the same time ample carbon source and higher C the N ratio benefits to take off to complete nitrogenously[7]
    4 The Carrousel oxidizes problem and solution methods of the ditch esse
    Though the Carrousel oxidizes the ditch has a water fluid matter good the anti pounds at the burthen ability strong divided by the phosphorus take off the nitrogen efficiency But in physically of movement process still exsits a series of problem
    41 Dirty mire inflation problem
    When discard the aquatic carbohydrate more the N P contains the unbalance of deal the pH value is low oxidizing the dirty mire in inside in ditch carries high fuse the oxygen density the shortage line up the mire not
    etc causes easily dirty mire in germ in form in silk inflationNot the dirty mire in germ in form in silk inflation takes place primarily at the waste water water temperature
    is lower but the dirty mire carries higher hourThe microbial burthen is high the germs absorbed the large quantity nourishment material is low because of the temperature metabolism the speed is slower accumulating the rises large quantity is high to glue sexual and many sugar materials making the surface of the live and dirty mire adhere to the water to increase consumedly SVI the value is very high becoming the dirty mire inflation
    Cause that aim at the dirty mire inflation can adopt the different counterplanFrom the anoxia water temperature high
    result in of can enlargement tolerance or lower into the water measures to alleviate burthen or the adequacy lowers the MLSS( control dirty mire reflux measure) making need the oxygen measures decreaseIf the dirty mire carries high can increase MLSS to adjust the burthen necessity the hour can stop into the water stuffy a period of timeCan pass the hurl add the nitrogen fertilizer phosphorus fatty adjust the admixture nourishment in the liquid material equilibrium( BOD5NP10051)The value of pH over low can throw to add the lime regulateBleach the powder with the liquid chlorin( press to fuck 03 of the dirty mire~06 the hurl adds) can repress the silk form germ breed controling the dirty mire in combinative water inflation[11]
    42 Foam problem
    Because entering to take the grease of large quantity in the water handling system can't completely and availably its obviation parts of greases enriches to gather in in the dirty mire through turn to brush the oxygen agitation creation large quantity foamThe mire is partial to long the dirty mire is aging and also easy creation foamSpray to pour the water or divided by with the surface the of do away with the foam in common use divided by the an organism oil kerosene the oil of silicon throw deal as 05~15 mgs LPass to increase dirty mire in pond in spirit

    in density or adequacies let up the tolerance of also can control the foam creation effectivelyWhen contain the live material in surface in the waste water more separate with the foam easily and in advance method or other methods do away withAlso can consider to increase to establish a set of divideding by the oil device moreoverBut enhance most importantly the headwaters manage reducing to contain the oil over the high waste water and other poisonous waste water of into[12]
    43 Float the problem on the dirty mire
    When contain in the waste water the oil measures big whole system mire quality become light can't like to control very much in operate process its at two sink the pond stop over time resulting in the anoxia easily producing the corrupt and dirty mire ascend to floatWhen spirit time over long take place in pond the high degree nitric turnthe function making nitrate density high at two sink the versa nitric in easy occurrence in pond turn the function creation nitrogen spirit make dirty mire ascend floatMoreover contain the oil in the waste water
    Take place the dirty mire ascend after floating should pause enter water broke off or dirty mire in clearance judge the clear reason adjust the operationThe dirty mire sinks to decline the sex bad can throw to add of oagulate or sloth materials the improvement precipitates the sexSuch as enter the water carries big let up into the water measures or the enlargement reflux measuresSuch as the dirty mire grain small lower the spirit machine turn soonIf discovers versa nitric turning should let up the tolerance enlarge the reflux or row the mire measuresIf discover the dirty mire is corrupt should enlargement tolerance the clearance accumulates the mire and try the ameliorative pond internal water dint term[12]
    44 Current velocity is not all and the dirty mire sinks to accumulate the problem
    In Carrousel oxidize ditch for acquiring its special admixture with handles result mix with liquid must with certain current velocity is in ditch circulate flowThink generally the
    lowest current velocity should should attain for an average current velocity for doing not take place sinking accumulating 03~05 ms sThe spirit equipments that oxidize the ditch is general to turn to brush for the spirit of to turn the dish with the spirit of turning to brush of immerse to have no depth for 250~300 mms turn the dish immerse to have no depth for 480~530 mmsWith oxidize the ditch water the deep(30~36 ms) comparing turn to brush occupied the deep 110~ in water 112 turned the dish to also occupy the 16~ only 17 therefore result in to oxidize the ditch upper part current velocity bigger( roughly 08~12 ms even larger) but the bottom currenvelocity is very small( especially at the water is deep 23 or 34 below mix with the liquid has no current velocity almost) causing ditch bottom large quantity accumulate the mire( sometimes accumulate the mire thickness amount to a 10 ms) the valid capacity that reduced to oxidize the ditch consumedly lowered to handle result affected a water fluid matter
    Adding the top downstream leads to flow the plank is a valid method that ameliorative current velocity distribute increases the oxygen ability with the most convenient measureThe upper stream leads to flow the plank installs at be apart from to turn the 40 places( upper stream) : dish( turn to brush) axis lead to flow plank high degree as the deep 15~ in water 16 combine the perpendicularity install in the surfaceThe downstream leads to flow the plank installs at be apart from to turn dish( turn to brush) axis 30 msLeading to flow knothole material can use metals or glass steels but regard glass steel as goodLead to flow the plank compares with other ameliorative measure can't not only increase the motive consumes with revolves cost but also can still than significantly exaltation 充 oxygen ability with theories motive efficiency[13]
    Moreover pass in the spirit on board swim to establish the underwater push machine can also turn to the spirit of the liquid of admixture that brush the bottom low speed area circulates to flow to rise positive push function from but the solution oxidizes the problem that low and dirty mire in current velocity in bottom in ditch sink accumulatesEstablish the underwater push machine useds for exclusively the push mixs with the liquid can make movement method that oxidize the ditch much more vivid this for economy energy lift the highefficiency having the very important meaning[14]
    5 Conclusion
    The Carrousel oxidizes the ditch because of having the good a phosphorus takes off the nitrogen ability anti pounds at the burthen ability with circulate to manage the convenience etc the advantage having got the extensive applicationBut because of technological development with social advance that craft is necessarily will exaltation getting furtherThe author thinksThe Carrousel oxidizes the future research direction of the ditch will now of main below several aspects
    1 Combination living creature method research with develop the living creature model Carrousel oxidize the ditchLike this can not only increases the microorganism gross of the unit reactor measures from but increases the organism carries but also living creature oneself the inside that have places the A the system of O enhances to take off the nitrogen result[18]
    2 Increases continuously the Carrousel oxidize the microbial activity in inside in ditchFor example throw to add the EM in oxidize ditch with single mind the germ grow throws in that the salt of iron make the microorganism tame the live char in iron devotion in living creature to become the formation to strengthen the germ gum regiment and increases to bear the toxicity pound at etc
    3 Increasing the Carrousel oxidizes the ditch equipments function with supervise and control the techniqueFunction that increases form machine underwater propeller reduce to maintain the workloadMaking use of DO etc of ORP many targets supervises and control the technique and changes the technique of is from now on the Carrousel oxidizes ditch science circulate necessarily from it road
    4 Increasing the Carrousel oxidizes the ditch resistant to cold and bear toxicity can reduce to cover the area to build the price with the engineeringTheoretical application deep pond in water power term with the research of the craft function is to lowers the engineering builds the price and increases resistant to cold bear the toxicity can wait to provide the possible direction
    氧化沟工艺污水处理中应发展
    摘: 文阐述Carrousel氧化沟结构工艺机理运行程中存问题相应解决方法介绍Carrousel氧化沟新研究进展指出未研究方
    关键词: Carrousel 氧化沟 磷脱氮 结构 机理
    Application and Development of Carrousel Oxidation Ditch Process on Wastewater Treatment
    Abstract The structure and the techniques of carrousel oxidation ditch process on nitrogen and phosphor removal are introduced in this paper The problems in running and their corresponding resolvent are also pointed At last The author showed the up to date research improvement and the mainly future research direction
    Key words Carrousel oxidation ditch nitrogen and phosphor removal structuretechniques
    1 前言
      氧化沟(oxidation ditch)名连续循环曝气池(Continuous loop reactor)活性污泥法种变形氧化沟污水处理工艺20世纪50年代荷兰卫生工程研究研制成功1954年荷兰首次投入出水水质运行稳定理方便等技术特点已国外广泛应生活污水工业污水治理[1]
      目前应较广泛氧化沟类型包括:帕斯韦尔(Pasveer)氧化沟卡鲁塞尔(Carrousel)氧化沟 奥尔伯(Orbal)氧化沟T型氧化沟(三沟式氧化沟)DE型氧化沟体化氧化沟氧化沟结构运行存差异具特点[2]文介绍Carrousel氧化沟结构机理存问题新发展
    2 Carrousel氧化沟结构
    Carrousel氧化沟1967年荷兰DHV公司开发研制原Carrousel氧化沟基础DHV公司美国专利特许公司EIMCO发明Carrousel 2000系统(见图1)实现更高求生物脱氮磷功世界已850座Carrousel氧化沟Carrousel 2000系统正运行[3]
      图见Carrousel氧化沟定控制曝气搅动装置混合液传递水速度搅动混合液氧化沟闭合渠道循环流动氧化沟具特殊水力学流态完全混合式反应器特点推流式反应器特点沟存明显溶解氧浓度梯度氧化沟断面矩形梯形面形状椭圆形沟水深般25~45m宽深21水深达7m沟中水流均速度03ms氧化沟曝气混合设备表面曝气机曝气转刷转盘射流曝气器导式曝气器提升式曝气机等年配合水推动器[4~6]

    图1 Carrousel 2000系统面结构图
    3 Carrousel氧化沟机理
    31 Carrousel氧化沟处理污水原理
    初普通Carrousel氧化沟工艺中污水直接回流污泥起进入氧化沟系统表面曝气机混合液中溶解氧DO浓度增加约2~3mgL种充分掺氧条件微生物足够溶解氧BOD时氨氧化成硝酸盐亚硝酸盐时混合液处氧状态曝气机游水流曝气区湍流状态变成流状态水流维持流速保证活性污泥处悬浮状态(均流速>03ms)微生物氧化程消耗水中溶解氧直DO值降零混合液呈缺氧状态缺氧区反硝化作混合液进入氧区完成次循环该系统中BOD降解连续程硝化作反硝化作发生池中结构限制种氧化沟然效处BOD磷脱氮力限[7]
      取更磷脱氮效果Carrousel 2000系统普通Carrousel氧化沟前增加厌氧区绝氧区(称前反硝化区)全部回流污泥1030污水进入厌氧区回流污泥中残留硝酸氮缺氧1030碳源条件完成反硝化绝氧池创造绝氧条件时厌氧区中兼性细菌溶性BOD转化成VFA聚磷菌获VFA化成PHB需量源聚磷水解导致磷酸盐释放厌氧区出水进入部安装搅拌器绝氧区谓绝氧池混合液分子氧化合物氧(硝酸根) 绝氧环境7090污水提供足够碳源聚磷菌充分释磷绝氧区接普通Carrousel氧化沟系统进步完成BOD脱氮磷混合液氧化沟富氧区排出富氧环境聚磷菌量吸磷磷水中转移污泥中剩余污泥排出系统样Carrousel 2000系统较时完成BODCOD脱氮磷[8]
      综合采该工艺昆明第污水厂[9]长沙市第二污水净化中心[10]漯河市污水处理厂运行效果见:Carrousel 2000系统处理BODCODSS率均达90TN率达80TP率达90
    32 Carrousel氧化沟磷脱氮影响素
      影响Carrousel氧化沟磷素污泥龄硝酸盐浓度基质浓度研究表明总污泥龄8~10d时活性污泥中磷含量干污泥量4异养菌体质量11污泥龄超15d时污泥中含磷量明显降反达磷效果味延长污泥龄(例20d25d30d)没必宜8~15d范围选时高硝酸盐浓度低基质浓度利磷程
      影响Carrousel氧化沟脱氮素DO硝酸盐浓度碳源浓度研究表明氧化沟存溶解氧浓度梯度氧区DO达3~35mgL缺氧区DO达0~05mgL发生硝化反应反硝化反应前提条件时充足碳源较高CN利脱氮完成[7]
    4 Carrousel氧化沟存问题解决方法
    Carrousel氧化沟具出水水质抗击负荷力强磷脱氮效率高污泥易稳定耗省便动化控制等优点实际运行程中存系列问题
    41 污泥膨胀问题
      废水中碳水化合物较NP含量衡pH值偏低氧化沟中污泥负荷高溶解氧浓度足排泥畅等易引发丝状菌性污泥膨胀非丝状菌性污泥膨胀发生废水水温较低污泥负荷较高时微生物负荷高细菌吸取量营养物质温度低代谢速度较慢积贮起量高粘性糖类物质活性污泥表面附着水增加SVI值高形成污泥膨胀
      针污泥膨胀起采取策:缺氧水温高造成加曝气量降低进水量减轻负荷适降低MLSS(控制污泥回流量)需氧量减少污泥负荷高提高MLSS调整负荷必时停止进水闷曝段时间通投加氮肥磷肥调整混合液中营养物质衡(BOD5:N:P100:5:1)pH值低投加石灰调节漂白粉液氯(干污泥03~06投加)抑制丝状菌繁殖控制结合水性污泥膨胀[11]
    42 泡沫问题
    进水中带量油脂处理系统完全效部分油脂富集污泥中转刷充氧搅拌产生量泡沫泥龄偏长
    污泥老化易产生泡沫表面喷淋水沫剂泡沫常沫剂机油煤油硅油投量05~15mgL通增加曝气池污泥浓度适减曝气量效控制泡沫产生废水中含表面活性物质较时易预先泡沫分离法方法外考虑增设套油装置重加强水源理减少含油高废水毒废水进入[12]
    43 污泥浮问题
    废水中含油量整系统泥质变轻操作程中控制二沉池停留时间易造成缺氧产生腐化污泥浮曝气时间长池中发生高度硝化作硝酸盐浓度高二沉池易发生反硝化作产生氮气污泥浮外废水中含油量污泥挟油浮
      发生污泥浮应暂停进水碎清污泥判明原调整操作污泥沉降性差投加混凝剂惰性物质改善沉淀性进水负荷应减进水量加回流量污泥颗粒细降低曝气机转速发现反硝化应减曝气量增回流排泥量发现污泥腐化应加曝气量清积泥设法改善池水力条件[12]
    44 流速均污泥沉积问题
      Carrousel氧化沟中获独特混合处理效果混合液必须定流速沟循环流动般认低流速应015ms发生沉积均流速应达03~05ms氧化沟曝气设备般曝气转刷曝气转盘转刷浸没深度250~300mm转盘浸没深度480~ 530mm氧化沟水深(30~36m)相转刷占水深110~112转盘占16~17造成氧化沟部流速较(约08~12m甚更)底部流速(特水深2334混合液没流速)致沟底量积泥(时积泥厚度达10m)减少氧化沟效容积降低处理效果影响出水水质
      加装游导流板改善流速分布提高充氧力效方法方便措施游导流板安装距转盘(转刷)轴心40处(游)导流板高度水深15~16垂直水面安装游导流板安装距转盘(转刷)轴心30m处导流板材料金属玻璃钢玻璃钢佳导流板改善措施相仅会增加动力消耗运转成够较幅度提高充氧力理动力效率[13]
      外通曝气机游设置水推动器曝气转刷底部低速区混合液循环流动起积极推动作解决氧化沟底部流速低污泥沉积问题设置水推动器专门推动混合液氧化沟运行方式更加灵活节约源提高效率具十分重意义[14]
    5 结
      Carrousel氧化沟具良出磷脱氮力抗击负荷力运行理方便等优点已广泛应科技发展社会进步该工艺必进步提高作者认:Carrousel氧化沟未研究方体现方面
    1 结合生物膜法研究开发生物模型Carrousel氧化沟样仅提高单位反应器微生物总量提高机负荷生物膜身具置AO系统强化脱氮效果[18]
    2 断提高Carrousel氧化沟中微生物活性例氧化沟中投加EM专菌种投入铁盐微生物驯化成生物铁投入活性炭增强菌胶团形成提高耐毒性击等
    3 提高Carrousel氧化沟设备性监控技术提高表曝机水推进器性减少维修工作量利DOORP等目标监控技术变频技术Carrousel氧化沟科学运行必路
    4 提高Carrousel氧化沟耐寒耐毒性减少占面积工程造价膜理应深池水力条件工艺性研究降低工程造价提高耐寒耐毒性等提供方
    参考文献:
    [1] Xia Shibin Liu Junxin An innovative integrated oxidation ditch with vertical circle for domestic wastewater treatment Process Biochemistry 2004 39(4)1111~1117
    [2] X Hao Doddema H J van Groenestijn J W Use of contact tank to enhance denitrification in oxidation ditches Water Science and Technology 1996 34(12)195~202
    [3] 汪雷乐成水处理新技术工程设计[M]北京化学工业出版社2000
    [4] 李正明导式氧化沟设计介绍化工排水设计19972:16~18
    [5] 朱谋溪吸式射流曝气器中型氧化沟中应水排水199925(8):13~18   
    [6] Dudley J Process testing of aerators in oxidation ditches Water Research 199529(9)2217~2219
    [7] Stamou Anastasios T Modeling of oxidation ditches using an open channel flow 1D advection dispersion equation and ASMI process description Water Science and Technology 199736(5)269~276 [8] Abusam A Keesman KJ van Straten G Forward and backward uncertainty propagation an oxidation ditch modelling example Water Research 200337(2)429~435
    [9] 施成忠昆明第污水厂氧化沟工艺运行实践分析中国水排水199713(3):17~19
    [10] 张华氧化沟工艺处理低浓度城市污水研究广西土木建筑199823(4):183~187
    [11] 潘玲徐潜张乐英氧化沟活性污泥膨胀原控制措施工业水废水200334(6):49~52
    [12] 吴昊刘庆臣李强利等氧化沟工艺运行中常见问题解决方法水排水200228(5):26~29
    [13] 曹瑞钰付见中改善氧化沟流速分布措施    中国水排水200117(2):16~18
    [14] 李伟民邓荣森王涛等水推动器氧化沟混合液循环作中国水排水200319(9):45~47
    [15] 黄伏根朱炳林微孔曝气Carrousel2000型氧化沟工艺处理城市污水冶金矿山设计建设200032(6):23~27





















    文档香网(httpswwwxiangdangnet)户传

    《香当网》用户分享的内容,不代表《香当网》观点或立场,请自行判断内容的真实性和可靠性!
    该内容是文档的文本内容,更好的格式请下载文档

    下载文档到电脑,查找使用更方便

    文档的实际排版效果,会与网站的显示效果略有不同!!

    需要 10 香币 [ 分享文档获得香币 ]

    下载文档

    相关文档

    城市污水处理A2O工艺毕业设计

    本设计是在**市新市镇新伍村拟建一座工程规模为6.09万m3/d的污水处理厂。通过综合考虑**市概况及本工程的规模、进水特性、处理要求、运行费用和维护管理等情况,经技术经济比较分析,确定采用A2...

    5年前   
    1260    0

    某污水处理厂设计倒置AAO工艺毕业设计

    某污水处理厂设计倒置AAO工艺毕业设计 摘 要 本次毕业设计的题目为xx市某污水处理厂工艺设计——倒置AAO工艺。设计主要任务是根据该市污水性质、排污规模的要求完成污水处理厂初步设计和单项...

    5年前   
    1538    0

    污水处理厂毕业设计

     污水处理厂毕业设计 目 录 第一章 设计概述 1 1.1 设计任务及设计依据 2 1.1.2 设计依据 2 1.2 设计水量与水质 2 ...

    5年前   
    1363    0

    东莞市污水处理厂升级改造工艺路线初探

    东莞市污水处理厂升级改造工艺路线初探摘要:针对东莞市38个污水处理厂的实际情况,通过对目前城市污水处理厂常用的二级处理工艺进行技术升级改造时可能采用的深度处理工艺技术的综合分析比拟,推荐了NP...

    4天前   
    38    0

    日处理水量15万吨城市污水处理厂工艺设计(氧化沟)毕业设计

    本科毕业设计(论文)任务书题 目:日处理水量15万吨城市污水处理厂工艺设计(氧化沟)院(系):专 业:环境工程学生姓名:学 号:指导教师(签名):主管院长(主任)(签名):时...

    3年前   
    612    0

    建模大赛设计CASS_工艺处理城镇污水毕业设计

    城镇生活污水厂处理工艺设计方案摘 要 本次大赛设计是以相关的资料为依据,设计一座城镇生活污水处理厂,其日处理量为20000 m3/dm。由于城市污水的主要成分为固体悬浮污染物(即SS)和...

    2年前   
    573    0

    青山湖污水处理厂和小蓝污水处理厂实习报告

    南昌航空大学2012~2013学年第二学期专业认识实习报告学 院:环境与化学工程学院专 业: 环境工程               班 级: 学     号: 姓     名:指...

    3年前   
    865    0

    污水处理厂生产实习报告

    污水处理厂生产实习报告  一、前言  众所周知,生产实习是学生大学学习很重要的实践环节,实习是每一个大学毕业生必的必修课,它不仅让我们学到了很多在课堂上根本就学不到的知识,还使我们开阔了视野、...

    11年前   
    882    0

    生活污水处理厂情况汇报

    **县生活污水处理厂情况汇报 为提升投资环境与改善人居环境,2006年10月,**县委、县人民政府决定建设污水处理厂。该项目于2006年10月25日进行公开招标,于2007年3月20日开工建...

    11年前   
    10380    0

    镇污水处理厂设计合同

      建设工程设计合同   (专业建设工程设计合同)       第一条 本合同签订依据。     1.1《中华人民共和国合同法》、《中华人民共和国建筑法》和《建设工程勘察设...

    9年前   
    7907    0

    污水处理厂实习体会

    污水处理厂实习体会  2、工艺控制  中央控制室:  对全厂主要运行设备监视、控制,中控室模拟屏可显示全厂运行动态及运行参数。控制系统计算机界面清晰、操作简单,具有运行情况显示,历史曲线显示,...

    9年前   
    773    0

    污水处理厂实习报告

    污水处理厂实习报告   .一   时不我待,转瞬就毕业一年了,回首过去一年,从找工作到现在要感谢的人许多,有许多收获,也有许多遗憾,“往者不行谏,来者犹可追”,对收获还是得感谢那些有声和...

    2年前   
    503    0

    污水处理厂实习报告

    污水处理厂实习报告  一.实习目的:   生产实习是学生大学学习很重要的实践环节。实习是每一个大学毕业生必的必修课,它不仅让我们学到了很多在课堂上根本就学不到的知识,还使我们开阔了视野,增长了...

    9年前   
    804    0

    污水处理厂半年总结

    2011年上半年我厂以节能降耗为目标,以不断提高我厂的管理水平及安全生产为重点,充分调动广大干部职工的积极性,稳步推进我厂的全年工作计划,确保我厂生产正常运行,现将北厂2011年上半年各项工作...

    5年前   
    2024    0

    污水处理厂运行情况

    污水处理厂 建设运行情况 一、基本情况 ***城市排水及污水治理工程项目于***年**月批复立项,建设内容及规模为新建日处理规模2万吨的污水处理厂一处,泵站一座,排水管线***公里,厂区...

    9年前   
    8766    0

    污水处理厂情况汇报

    污水处理厂情况汇报  麻涌镇污水处理厂是麻涌镇xx期间最重要的环保项目,是东莞市第二批以特许权(bot)方式进行建设的污水厂之一。东莞市豪丰环保投资集团下属子公司东莞市豪丰污水处理有限公司作为...

    11年前   
    801    0

    污水处理厂建设项目

      湖北省咸宁市双溪桥镇污水处理厂建设项目 1.1.1 项目名称 湖北省咸宁市双溪桥镇污水处理厂建设项目 1.1.2 项目法人 湖北省咸宁市双溪桥镇污水处理厂建设项目指挥部 1.1...

    12年前   
    12904    0

    高校生污水处理厂实习报告

    高校生污水处理厂实习报告高校生污水处理厂实习报告1   前言   水是生命之源,更是我们人类能够可持续进展的动力保障。随着.的高速进展,资源的不合理利用,目前,水体变质的环境问题给我们的...

    2年前   
    485    0

    2021年污水处理厂总结-总结

    2021年污水处理厂总结-总结 篇一:2021污水处理个人工作总结 2021污水处理个人工作总结 污水处理个人工作总结 光阴似箭,时间如梭。转瞬间上班已经一年了,回首过去...

    3年前   
    649    0

    污水处理厂考察资料

    XXXXXX污水处理厂考察资料   公开资料: 企业(机构)名称:XXXXXXXXX污水处理有限公司 市场主体类型:有限责任公司 成立日期:20XX年0X月0X日 法定代表人:...

    9年前   
    8033    0

    文档贡献者

    z***u

    贡献于2019-05-22

    下载需要 10 香币 [香币充值 ]
    亲,您也可以通过 分享原创文档 来获得香币奖励!
    下载文档